Skip to main content

This open house ran May 3-31, 2024. The content may no longer be current.

Please visit the project webpage for current information.

All dates are estimates and subject to change.

 
  • Council Creek Regional Trail Master Plan (Metro)

    2015
  • Planning phase

    2021-2024

    Included online and in-person open houses.

  • East-West Trail design begins

    Spring 2024
  • East-West Trail design online open house

    May 3-31, 2024

    You are here.

  • East-West Trail final trail designs complete

    August 2024 (expected)
  • East-West Trail final street crossings design begins

    Spring 2025 (expected)

    Two additional open houses are planned during street crossing design.

  • East-West Trail street crossing design complete

    Spring 2026 (expected)
  • Bid for construction contractor

    Spring 2026 (expected)
  • East-West Trail construction

    Summer 2026-spring 2028

    Bridge construction can only occur during an in-water work window: July-September. Trail construction will include two in-water work windows to complete all of the work within the floodplain.

  • North-South Trail design and construction

    Dependent on funding