All dates are estimates and subject to change.
-
Council Creek Regional Trail Master Plan (Metro)
2015 -
Planning phase
2021-2024Included online and in-person open houses.
-
East-West Trail design begins
Spring 2024 -
East-West Trail design online open house
May 3-31, 2024You are here.
-
East-West Trail final trail designs complete
August 2024 (expected) -
East-West Trail final street crossings design begins
Spring 2025 (expected)Two additional open houses are planned during street crossing design.
-
East-West Trail street crossing design complete
Spring 2026 (expected) -
Bid for construction contractor
Spring 2026 (expected) -
East-West Trail construction
Summer 2026-spring 2028Bridge construction can only occur during an in-water work window: July-September. Trail construction will include two in-water work windows to complete all of the work within the floodplain.
-
North-South Trail design and construction
Dependent on funding